Plain answer. Hire the owner's representative before the general contractor, because the decisions that set cost and schedule are made before a contractor is selected. The contractor builds what has already been decided. The representative makes sure those decisions are the owner's.
Four hats, four incentives
When an owner starts a data center project, four kinds of firms will offer to lead it. Each one is useful. Each one is paid differently, and the way a firm is paid tells you whose interest it protects when something goes wrong.
| Role | Paid by | Incentive | Accountability ends |
|---|---|---|---|
| Owner's representative | The owner, for management of the whole program | The owner's outcome: capital protected, capacity delivered on the plan | At commissioned handoff and tenant readiness |
| General contractor | The owner, for the build | Deliver the scope in the contract at the agreed margin | At substantial completion of the construction scope |
| Developer | Its own capital and the eventual sale or lease | Own and monetize the asset | When the asset is sold or leased |
| Broker | A commission on the transaction | Close the deal | At signing |
None of these incentives are wrong. A contractor should protect its margin. A developer should want the asset. The problem is when an owner expects one of them to do a job it is not paid to do.
Where each one's accountability stops
The general contractor's scope starts at the drawings and ends at substantial completion. Utility delays, tenant changes, equipment that was never ordered and a commissioning plan nobody wrote are outside the fence. The contractor will tell you so, correctly.
The developer's model works when the developer owns the asset. If you are the owner, a developer is either buying you out or competing with you for the same tenant and the same power.
The broker's work is done when the paper is signed. Everything that makes the paper true happens afterward.
The owner's representative is the only one of the four whose scope is the whole program and whose client is the owner alone.
The fragmented handoff problem
Here is what fragmentation looks like in practice. The broker closes the land. A consultant runs the utility study. An engineer produces a basis of design from assumptions the utility has not confirmed. The owner issues purchase orders to three vendors because each one had the best price. The contractor mobilizes. Then the transformer date moves, the tenant wants a different density and nobody can tell the owner which of those two things is the critical path, because nobody is holding the whole schedule.
Every party did its job. The owner is still the one explaining the slip to the lender.
What changes when one party owns the interfaces
With an owner's representative in place, each specialist still does its work under its own contract. What changes is that the dates, deliverables and decisions now sit in one integrated schedule, one data room and one approval matrix. Drift shows up as a decision the owner makes this week instead of a field problem the owner discovers next quarter.
The owner's approval rights do not shrink. They become usable, because the information arrives in time to use them.
Five questions to ask any firm that says it does it all
- Who is your client on this project, and who else is paying you?
- Where does your scope end, in writing?
- Who holds the integrated schedule, and can I see it every week?
- If the tenant changes the density, who re-sequences procurement and who approves the cost?
- Do you want to own this asset?
The answers will tell you which hat you are talking to.
Questions & answers.
It can offer to. Its contract is for the build, and its margin is in the build. The owner's interests in power, procurement, tenant fit and commissioning sit outside that contract.
J-Box